Project Description

Regional Municipality of Niagara
Niagara Falls, Ontario

Procon was the prime contractor for this project. The Garner Road Biosolids Facility makes sludge cake by dewatering anaerobically digested sludge that is trucked in from wastewater treatment plants in the area.
Procon completed the mechanical, electrical and SCADA portions of the work in house as well as coordinating numerous subcontractors and suppliers. Mainly the job consists of supplying and installing a new dewatering centrifuge, polymer preparation/feed equipment, sludge grinding/feed equipment and modifications to existing screw conveyors. Once the upgrade is complete the plant’s biosolids production capacity will be doubled.