This project consisted of the demolition and restoration of the Welland Water Treatment Plants 1 and 2. The removal of the existing pumps, process piping, valves and chemical systems to make way for the newly restored processes.
Highlighted areas of our scope of work consisted of the supply and installation of:
The new high lift plant was constructed and commissioned prior to the decommissioning of the existing plant. All works were completed without interruption to the plant processes and water supplies to the client.